About S4 Burhafe

Located in Lower Saxony, S4 Burhafe is a 15 MW / 30 MWh grid-scale battery energy storage system adjacent to the EWE substation in the municipality of Wittmund. As one of S4 Energy’s first German projects to reach Ready-to-Build status, Burhafe represents a key milestone following the acquisition of Terra One’s German development portfolio. The project strengthens regional grid stability and supports the integration of renewable energy into one of Germany’s rapidly evolving power markets.

BESS Burhafe is ready to build, with energisation targeted for Q4 2026. The project is being developed in close coordination with the local municipality, landowner, and grid operator, EWE Netz, and reflects S4 Energy’s ambition to scale flexible storage solutions across Europe.

Project Details

Capacity 15 MW / 30 MWh
Duration 2 hours
Expected COD Q4 2026
Location Wittmund, Lower Saxony, Germany
Grid Operator EWE Netz
BESS OEM/EPC OEM CATL via EPC Alfen

S4 Energy Zeeland 3 van 20

Project Highlights

  • One of S4 Energy’s first German BESS projects
  • First project from the Terra One pipeline to reach Ready-to-Build
  • Direct grid connection adjacent to the EWE substation
  • Supports regional grid stability and renewable integration
  • Developed in collaboration with municipality and landowner

Impact

It is estimated to avoid up to 31.042 tonnes of CO₂ emissions per year, equivalent to:

  • Approximately 17,000 cars taken off the road
  • Clean power flexibility comparable to 16,600 homes annually
  • Avoiding the emissions of roughly 8,623 flights
  • Comparable to the annual CO₂ absorption of 1,410,977 trees
Screenshot 2026 01 09 at 09 34 39

Frequently Asked Questions

BESS Burhafe contributes to Europe’s energy transition by increasing grid flexibility and enabling the efficient integration of renewable energy. By providing 15 MW / 30 MWh of fast-responding storage capacity at a direct grid connection, the project helps stabilise the regional electricity network, reduce congestion, and manage the intermittency of wind and solar generation—key challenges in Europe’s decarbonising power system.

Burhafe is one of S4 Energy’s first German projects and the first project from the Terra One portfolio to reach Ready-to-Build status. Strategically, it marks S4 Energy’s formal entry into the German market and represents an important milestone in the company’s ambition to become a leading flexibility provider across Europe.

The project combines a direct grid connection in a rural location with grid-scale battery storage to deliver targeted regional grid stabilisation. In addition, Burhafe is expected to integrate ecological compensation measures, such as native planting and multi-year maintenance, aligning technical performance with S4 Energy’s broader sustainability standards.

Health, safety, and environmental protection protocols are fully integrated into the project’s development approach. S4 Energy is working with the municipality, landowner, and a specialised EPC contractor (to be appointed) to ensure compliance with all applicable technical, environmental, and regulatory standards throughout construction and operation.

The project is located in a rural area, minimising residential impact. Close coordination with the municipality of Wittmund and the landowner ensures compliance with environmental and legal requirements. While public participation has been limited, the project delivers local and societal value by strengthening grid reliability, supporting the regional energy transition, and contributing to the common good through improved system stability.